KRIBHCO – SURAT
Major Milestone For Hazaria Plant
   
   PIB Clearance for the Project

17.04.1980

 
   
   Land acquisition

07.07.1980

   
   Project Zero Date


31.03.1981


   Foundation Stone laying by Late Prime Minister Smt. Indira    Gandhi


05.02.1982
   
   Mechanical completion of Plants :


a. 1st Phase of Ammonia & two streams of Urea plants

b. 2nd Phase of Ammonia & two streams of Urea plants




30.04.1984

31.08.1984


   
   Receipt of gas for - Phase-1

   Receipt of gas for - Phase-2


18.09.1985

06.11.1985



   Commencement of Trial production - Ammoni

   Urea


14.11.1985

26.11.1985



   Start of Commercial Production - Ammonia & Urea

01.03.1986